DIRECTIONS for the question: Solve the following question and mark the best possible option.

X, Y, Z can do a piece of work in 4, 8, 12 days respectively. In how many days they together will do the same work?
A)
1/11 days
B)
2 days
C)
13/24 days
D)
24/11 days