DIRECTIONS for the question: Solve the following question and mark the best possible option.

A can do a piece of work in 24 days and B can do the same piece of work in 36 days. A and B together complete the same piece of work and get Rs. 2000 as the combined wages. A’s share of the wage will be
A)
Rs. 800
B)
Rs. 900
C)
Rs. 1000
D)
Rs. 1200