A and B can do a piece of work in 4 days, B and C in 6 days and A and C in 9 days. A, B and C can together complete the work in how many days?
A)
B)
C)
D)
None of these
B
Hence option B.
Question include in Following Tests :
Work & Chain Rule Level I - 04
Upload Final Test
LLB DU Mock Test - 02
Upload Final Test
Placement Cognizant GenC 01
Upload Final Test
PDF - MAT - Mathematical Skills 03
Upload Final Test
Placement Cognizant GenC 09
Upload Final Test
Mock Placement - 16
Upload Final Test
CUETQ Section Test - 05
Upload Final Test
Cognizant Quant 01
Upload Final Test
CUET - Time & Work - PE 03
Upload Final Test
LPU AE 24 - Analytical Test 02
Upload Final Test
CUET PG - Time & Work - PE 03
Upload Final Test
CPT - Time & Work
Upload Final Test
CPT Cognizant GenC 04 (Round 1)
Upload Final Test